Council will be upgrading footpaths in Katoomba Town Centre from 25 February 2021.

The continued improvement of the Town Centre footpaths is funded with $870,000 from the Local Roads and Community Infrastructure Program.

This follows footpath improvements delivered at Bathurst Road to the Carrington Hotel in 2012 and near the post office and Pioneer Place in 2014.

The new project will see delivery of a new footpath, kerb and gutters from the southern side of the pedestrian crossing on Gang Gang Street, continuing down the eastern side of Katoomba Street to the Council car park (next door to St Canice's Primary School).

Tree plantings will remain and Council will refurbish any impacted street furniture.

This upgrade will start 25 February 2021 and is expected to finish in May 2021.

The work take place in three stages:
•    Stage 1: Theo Poulos to Katoomba Wines - Thurs 25/02/21 to Fri 26/03/21
•    Stage 2: Omnia to Specsavers - Mon 22/03/21 Sat 24/04/21
•    Stage 3: National Bank to Council Car Park - Mon 26/04/21 Fri 21/05/21

All dates are weather dependent.

Works will occur during the day, 7am-6pm Monday to Friday (and if necessary, 7am-3pm Saturday). Work on the Telstra pits will occur during the night to ensure minimum disruption to business and residents.

For more information, phone Project Manager Jane Lambert on 4780 5497 or email jlambert@bmcc.nsw.gov.au.